SAP MIGO Partial Goods Receipt of a PO

SAP MIGO Partial Goods Receipt of a PO

1. Go to T_code : MIGO

2. Select Goods Receipt
3. Select Purchase Order
4. Enter PO number for goods to be received.
5. Hit "Enter"


6. Enter Document date & posting date
7. Enter Header text (comment) if necessary.
8. Close detail data.


9. Notice that movement data is "101"
10. If you only received first item, then Check the "OK" box for first line item.
therefore, the second item need not be processed



10. If you only received 3 pcs out of 10 pcs of item one & 2 pcs out of 10 pcs of item two, then Check the "OK" box for both line item

11. Input actual quantity (3 & 2 pcs ).
12. Hit "Enter"


11. Click "Check" button to find out if there is any error.
12. Check the "status" column .
. Green means OK
. Yellow means Warning
. Red means error
13. This is just a warning that there are still quantities yet to be processed in this PO.
14. Click the "check mark"









SAP MIGO Goods Receipt all items in a PO

SAP MIGO Goods Receipt all items in a PO.

1. Go to T_code : MIGO

2. Select Goods Receipt
3. Select Purchase Order
4. Enter PO number for goods to be received.
5. Hit "Enter"


6. Enter Document date & posting date
7. Enter Header text (comment) if necessary.
8. Close detail data.


9. Notice that movement data is "101"
10. Check the "OK" box.

11. Click "Check" button to find out if there is any error.
12. Check the "status" column .
. Green means OK
. Yellow means Warning
. Red means error

13. Post, If the message is "Document is OK"


14. Noted the document number.





SAP Create SO in HQ (Supplier) from subsidiary PO data

SAP Create SO in HQ (Supplier) from subsidiary (Buyer) PO data

Normally used for intercompany transaction.

If Subsidiary A raise PO with pricing to HQ.
It doesn't have to be a special pricing procedure.
You can choose the following :
- 1-step move with no billing/delivery (intercompany 301),
- 2-step move with no billing/delivery (intercompany 351),
- 2-step move with delivery,
- 2-step move with delivery and billing

You may configure where buyer (normally subsidiaries in the same group) can create Sales Order in supplier (normally Head Quarter).

These are all standard out of the box, and data flows naturally from document to document.
The invoice can cause the invoice receipt to be automated, but it relies on a little EDI setup.

If Buyer A raise a PO on HQ and HQ raise Delivery against the buyer PO.
You can dictate in the billing create from delivery that the price be adopted from originating PO.

Ensure that you have a price condition in SD that matches the name of the price condition used in the PO, then in VTFL at item level, set Pricing Souce B - Purchase Order/Delivery.

This set-up can reduce a workload to issue SO one by one in HQ which has many subsidiaries raise PO on HQ.

Subsidiary must have a authorized person to approve PO which will create SO in HQ.

Each subsidiary will be given a different Tcode
e.g : Subsidiary A :ZPT114R010, Subsidiary B :ZPT114R011

The sample below is not standard SAP.

1. Below is the sample after a subsidiary enter the Tcode ZPT114R010

2. Please enter some search conditions.
If you don’t enter search condition, the procedure will be very slow.
I recommend you to enter search conditions as many as possible.

3. Click the “Execute” icon.


4. The POs only such that the Document type of which is ZOC and the vendor of which is Head Quarter are displayed.

Approve the lines whose statuses are Red Signal.
Please select the line which you want to approve.

■■■In case that there are plural line items for single PO, each line item is displayed.
Select all line items which have the same PO number and approve them. ■■■

5. Click “Approve” icon.


6. Please check the message and the statuses of the lines.


The status will be Green after approving


7. You can check the status of approving at the right of this screen.
There is information : Approved by, approved date & time, etc





SAP ME2L Overview Pending PO

SAP ME2L Overview Pending PO

1. Go to Tcode ME2L


2. Click "get variant" icon


3. Select variant which you have been saved.

4. Click "OK" icon




5. The below screen will be appeared

6. Enter purchasing organization

7. Enter purchasing group

8. Enter Plant


9. List of Pending PO will be displayed.

SAP ME22N Change Purchase Order

SAP ME22N Change Purchase Order

1. Go to Tcode ME22N


2. Make sure that Goods Received & Invoice Verification were already reverse.

3. Highlight all line items and click "trash" icon


4. Click "Yes" to the warning.


5. Save

6. Notice the message


7. By pass the warning message by hitting enter.

8. Noted the document number.



SAP MIGO Adjustment of Physical Inventory Difference

SAP MIGO Adjustment of Physical Inventory Difference

Case :
Company physical inventory has different quantity with SAP Inventory quantity.
The physical inventory is 2 units more than book keeping.

※In this Scenario, the quantity is increased.
For decreasing (GI), be sure of using the other Mvt. Type.

Mvt Type 701 : Increasing (GR Phys. Inventory)
702 : Decreasing (GI Phys. Inventory)

1. Go to Tcode : MIGO


2. Select "Goods Receipt"
3. Select "Others"
4. Select Movement type "701".
5. Click "Material" tab
6. Enter Material Code


7. Click "Quantity" tab
8. Enter quantity to increase.


9. Click "Where" tab
10. Enter plant & storage
11. Make sure movement type is correct.


12. If this screen is appeared, please hit “Enter” key to extinguish this screen.


13. Click "Check" icon.
14. Post if the message is "Document is OK"


Back

SAP MIGO reduce inventory for obsolete material

SAP MIGO Reduce Inventory for disposal, obsolete, internal and other usage material except sales

1. Go to Tcode MIGO


2. Select "Goods Issue"
3. Select "Others"
4. Enter date
5. Select moving type : "551"
6. Click "material" tab
7. Enter material code



8. Click "Quantity" tab
9. Enter quantity of inventory you want to reduce

10. Select "where" tab.
11. Enter plant and storage
12. Check movement type.



13. Select "Account Assignment" button.
14. Enter suitable G/L account code
e.g. obsolete material account code.
Default account code will be used if we do not enter in this field.
15. Enter "cost center".





16. Click "check" button.


17. SAVE, If "the document is OK" message displayed.


18. Noted the document no.


Back

SAP ME21N Create Purchase Order

SAP ME21N CREATE PURCHASE ORDER

Go to T.code ME21N


1. Choose Order type


2. Enter Vendor

3. Enter Document Date

4. Enter Organization group

5. Enter Material code
Note : you can overwrite material description if necessary


6. Enter P.O. Quantity

7. Enter Net Price

8.
Delivery date by default is the same with document date

Enter Delivery date if necessary
9. Enter Plant

Hit "Enter" button



10. Enter storage date



11. You may add line item as neccessary


12. At this point showing line item detail 10's information.


13. To check Net Price go to "condition" tab

Notice the relation of the price

14. Add comment at the header "texts" tab if neccesary


15. Click "check" icon to see whether there are errors/warnings.


Note that document with error cannot be saved.

16. Note the saved document number.

Use Tcode ME23N to view this document

























SAP ME23N Display Purchase Order

SAP ME23N TO VIEW PURCHASE ORDER

A Purchase Order document is divided into 3 sections:
1. Header
Contains information of the document as a whole
*This section includes the document currency and Net price info
2. Item Overview
Contains a summarized information of all items (materials)
3. Item Detail
Contains a detailed information of each item (material)
*This section includes each item price and history (if applicable)

Click the icon to expand or collapse


Back